J M Baxi Heavy successfully completed the load out of a living quarters module, to be installed at Bombay high offshore field for ONGC. The modules weighing 3900 ton was loaded out at the L&T Hazira yard with the help of 180 axles. This is the last of 7 modules loaded out for the NLRNC Mumbai high project. All the modules weighing a total of 22,860 tons or 440000 freight ton were transported within a short span of 45 days using a total of 1130 axles.