Home » News » JNPT takes mitigation measures in view of Cyclone Tauktae

JNPT takes mitigation measures in view of Cyclone Tauktae

JNPT Chairman, Shri Sanjay Sethi, IAS along with Deputy Chairman, Shri Unmesh Sharad Wagh, IRS chaired a high level meeting with the stakeholders to review the preparedness of the port.
Facebook
Twitter
LinkedIn
WhatsApp
Email

JNPT has taken various mitigating measures, in view of the ‘Cyclone Tauktae’. The Indian Meteorological Department (IMD) has issued cyclone warning for the area and JNPT is likely to experience heavy weather and sustained high wind speeds due to which various steps are being taken to mitigate the impact of the cyclone on the port property and ships in JNPT waters.

JNPT Chairman, Shri Sanjay Sethi, IAS along with Deputy Chairman, Shri Unmesh Sharad Wagh, IRS chaired a high level meeting today with the stakeholders to review the preparedness of the port to deal with the situation arising out of Cyclone ‘Tauktae.’

The port has planned to sail out all the vessels at berth by 2300 hrs on 15th May, 21. Also all inward Shipping movements will remain suspended till easing of weather conditions. During the meeting it was also decide that all crafts of ITDC Cementation and those engaged in the construction activities of MTHL phase 2 are advised to secure alongside; ships anchored in Bravo East / West outer anchorage are advised to take all necessary steps for their safety which includes steaming out to High seas; ONGC Nhava Base to ensure that the M.T. Blossom and OSVs at berth are ready to sail out by 2300 hrs on 15/5/21 and all Terminals were advised to secure their Cargo handling gear and other related equipment and comply with the heavy weather contingency plan.

During the meeting it has been conveyed that all cranes at all the terminals will be secured by tie-down anchors and passenger launch services from JNPT to Mumbai will remain suspended till further notice.

JNPT has opened a control room for three days from today. May 15 to May 17, 2021. And the officer posted at the control room have been advised to coordinate and submit report to the concerned HOD. The port is continuously in touch with IMD and are updating them in regular intervals.

Facebook
Twitter
LinkedIn
WhatsApp
Email

Subscribe to Our Newsletter

One Ocean Maritime Media Private Limited
Email
Name
Share your views in comments